Mill Creek/Peaks Branch/State-Thomas Drainage Relief Tunnel project started in March 2018 and scheduled to complete in 2023. Timeline below provides scheduled construction activities in various areas East of the downtown. Click the maps on this page to view the construction areas, and most up-to-date construction impacts in an area can be found here.

2018

Spring Notice of Proceed Issued
Summer

Outfall shaft construction in Hwy 352/Dixon Ave starts

Street work in Hwy 352/Dixon Ave starts

Fall

Shaft construction at Haskell Ave/Ross Ave starts

Shafts construction in Fair Park Area starts

Street work in Buckner Park Area starts

Street work in Hwy 352/Dixon Ave ends

Fair Park Area
Hill Ave. at I-30 Area
Buckner Park Area
Haskell Ave./Ross Ave. Area
Woodall Rodgers Freeway Area
Highway 352/Dixon Ave. Area