Home
About
Progress Photos and Maps
Street Closures
News
Contact Us
Back
Project Overview
Project Timeline
Meet Our Team
Street Improvement Drawings
Back
Renderings
Site A
Site C
Site D
Site E
Site F
Site O
Tunnel
Tunnel Excavation Status Map
Home
About
Project Overview
Project Timeline
Meet Our Team
Street Improvement Drawings
Progress Photos and Maps
Renderings
Site A
Site C
Site D
Site E
Site F
Site O
Tunnel
Tunnel Excavation Status Map
Street Closures
News
Contact Us
Site D - Buckner
May 2022 - Shaft D
March 2022 - Shaft D
March 2022 - Shaft D Excavation
February 2022 - Excavation for Stormwater Line installation in Gaston Avenue and N. Carroll Avenue intersection
January 2022 - Asphalt Overlay on N. Carroll Avenue
December 2021 - N Carroll Avenue Sidewalk
November 2021 - N Carroll Avenue Street Restoration
October 2021 - Concrete Pavement on N Carroll Avenue (from Worth St. to Junius St.)
September 2021 - 9'X9' Stormwater Line Installation in N. Carroll Avenue
August 2021 - Stormwater Lateral installation in the Junius St. and N. Carroll Ave. intersection
July 2021 - Wastewater Line through Stormwaterline in the Victor St. & N Carroll Ave. intersection
June 2021 - 9'X9' RCBs staged on N Carroll Avenue for installation